Contract 73354 REL 7: 2007-401-00 EXP BIOP KELT RECONDITION/REPRODUCTIVE SUCCESS 2018
Project Number:
Title:
Kelt Reconditioning and Reproductive Success Evaluation Research
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Plateau Snake Lower 100.00%
Contract Number:
73354 REL 7
Contract Title:
2007-401-00 EXP BIOP KELT RECONDITION/REPRODUCTIVE SUCCESS 2018
Contract Continuation:
Previous: Next:
76548: 2007-401-00 EXP BIOP KELT RECONDITION/REPRODUCTIVE SUCCESS 2017
  • 73354 REL 27: 2007-401-00 EXP KELT RECONDITIONING/REPRODUCTIVE SUCCESS 2019
Contract Status:
Closed
Contract Description:
The Kelt Reconditioning and Reproductive Success Evaluation Project is a research, monitoring, and evaluation (RM&E) uncertainties category project funded through the Columbia Basin Fish Accords.  The objectives are to evaluate methodologies to produce viable artificially reconditioned repeat steelhead spawners and to determine the productivity of repeat spawners.  Work occurs in both the Yakima and Snake river basins.  We focus on collecting steelhead kelts at juvenile bypass facilities in Prosser and Lower Granite dams, and additionally some fish are collected at Dworshak National Fish Hatchery.  These kelts were reconditioned (given prophylactic treatments and fed a specially formulated diet) at Prosser and Dworshak National Fish Hatcheries.  Survival of long-term reconditioned kelts has been 42% (17 years) for Yakima River at Prosser Hatchery and at Dworshak Hatchery 21% (5 years) for hatchery origin fish, 33% (6 years; 46% over the last 4 years) for mixed stock collections at Lower Granite Dam, and in previous years Fish Creek and the South Fork Clearwater River.  

Experiments are conducted to better understand the survival and rematuration process and investigate optimum management scenarios for reconditioned fish.
Account Type(s):
Expense
Contract Start Date:
07/01/2018
Contract End Date:
06/30/2019
Current Contract Value:
$1,806,901
Expenditures:
$1,806,901

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

BPA COR:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Environmental Coverage Documents A: 165. Produce Environmental compliance document for kelt activities 06/30/2019 06/30/2019
Collection of kelt steelhead B: 66. Collect, hold, and transport kelt steelhead for experiments 06/30/2019 06/30/2019
Biological data collection on adult steelhead C: 157. Collect biological data and tissue for genotyping from adult steelhead 06/30/2019 06/30/2019
PIT tagging adult steelhead D: 158. PIT tag adult steelhead at collection sites 06/30/2019 06/30/2019
Rear kelt steelhead E: 176. Recondition kelt steelhead for long term treatments 06/30/2019 06/30/2019
Collection of biological data from reared fish F: 157. Collect survival, condition, and rematuration data on reared kelt steelhead 06/30/2019 06/30/2019
Data analysis G: 162. Analyze kelt steelhead post rearing data 06/30/2019 06/30/2019
Generate Genotypic data H: 157. Genotype tissue samples from adult and kelt steelhead, and from resident O. mykiss 06/30/2019 06/30/2019
Conduct genetic analysis I: 162. Conduct parentage assignments, and stock identification from genetic data 06/30/2019 06/30/2019
Gamete and Progeny viability study J: 157. Collect gamete and progeny viability data from kelt steelhead 06/30/2019 06/30/2019
Interpret Gamete and Progeny Viability Data K: 162. Interpret gamete and progeny viability data from kelt steelhead 06/30/2019 06/30/2019
Implement Snake River Kelt Reconditioning Research Plan L: 157. Implement Snake River Kelt Reconditioning Plan 06/30/2019 06/30/2019
Compete the 3 step process for a Snake River Kelt Reconditioning Facility M: 196. Complete 3 Step Process for a Snake River Kelt Reconditioning Facility 06/30/2019 06/30/2019
Produce Presentations N: 161. Present findings with presentations 06/30/2019 06/30/2019
Work toward submitting a peer-reviewed journal article O: 183. Work toward submitting a peer-reviewed journal article 06/30/2019 06/30/2019
Attach Hatchery Reconditioning Plan P: 174. Hatchery Reconditiong Plan 06/30/2019 06/30/2019
Effective implementation management and timely contract administration Q: 119. Manage project and subcontracts for kelt project 06/30/2019 06/30/2019
Upload 2018 Annual Report R: 132. Submit 2018 Annual Report for January 2018 to December 2018 03/31/2019 03/15/2019
Submit BiOp RPA Report in Taurus S: 202. BiOp RPA Report for CY 2018 03/15/2019 03/15/2019

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Steelhead (Oncorhynchus mykiss) - All Populations
  • 1 instance of WE 161 Disseminate Raw/Summary Data and Results
Steelhead (O. mykiss) - Middle Columbia River DPS (Threatened)
  • 1 instance of WE 176 Produce Hatchery Fish
  • 1 instance of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 183 Produce Journal Article
  • 4 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 158 Mark/Tag Animals
  • 2 instances of WE 162 Analyze/Interpret Data
Steelhead (O. mykiss) - Snake River DPS (Threatened)
  • 1 instance of WE 196 Council Step Process
  • 1 instance of WE 176 Produce Hatchery Fish
  • 1 instance of WE 66 Trap/Collect/Hold/Transport Fish - Hatchery
  • 1 instance of WE 174 Produce Plan
  • 1 instance of WE 183 Produce Journal Article
  • 4 instances of WE 157 Collect/Generate/Validate Field and Lab Data
  • 1 instance of WE 158 Mark/Tag Animals
  • 2 instances of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 165 Produce Environmental compliance document for kelt activities 07/01/2018
B 66 Collect, hold, and transport kelt steelhead for experiments 07/13/2018
C 157 Collect biological data and tissue for genotyping from adult steelhead 07/13/2018
D 158 PIT tag adult steelhead at collection sites 07/13/2018
E 176 Recondition kelt steelhead for long term treatments 07/13/2018
F 157 Collect survival, condition, and rematuration data on reared kelt steelhead 07/13/2018
G 162 Analyze kelt steelhead post rearing data 07/01/2018
H 157 Genotype tissue samples from adult and kelt steelhead, and from resident O. mykiss 07/13/2018
I 162 Conduct parentage assignments, and stock identification from genetic data 07/01/2018
J 157 Collect gamete and progeny viability data from kelt steelhead 07/13/2018
K 162 Interpret gamete and progeny viability data from kelt steelhead 07/01/2018
L 157 Implement Snake River Kelt Reconditioning Plan 07/13/2018
M 196 Complete 3 Step Process for a Snake River Kelt Reconditioning Facility
N 161 Present findings with presentations 07/01/2018
O 183 Work toward submitting a peer-reviewed journal article 07/01/2018
P 174 Hatchery Reconditiong Plan 07/13/2018
Q 119 Manage project and subcontracts for kelt project 07/01/2018
R 132 Submit 2018 Annual Report for January 2018 to December 2018 07/01/2018
S 202 BiOp RPA Report for CY 2018
T 185 Quarterly Status Reports for BPA 07/01/2018